December 142018

Overnight Work at South Bus Loop and Passenger Platform at Kennedy Station

What Work is Taking Place?

In support of construction of the future Kennedy Station, crews will be installing wet utilities pipes in the south bus loop and passenger platform area at Kennedy Station.

Working will involve removing existing concrete and excavating a trench followed by installation of the pipe and area restoration. To minimize disruption to transit users, the work will be performed overnight. Read more »

December 142018

Test Isolation of a Watermain

WATERMAIN ISOLATION

 

WHAT WORK IS TAKING PLACE?

 

On December 20th, crews will perform a test isolation of a watermain located between Oriole Parkway and Eastbourne Avenue. There are no known services connected to this main and thus no anticipated impacts however should you experience a disruption please contact Crosstown Community Office 24 hours at 416-782-8118.

 

 

TIMING Read more »

December 142018

Green Wall Construction Continues at the E.T. Seton Park

What Work is Taking Place?

As part of the construction of the future Sunnybrook Park Stop, crews will continue construction of a green wall (retaining wall) at the E.T. Seton Park along the south side of Eglinton Avenue East at Leslie Street intersection as part of the construction of the Eglinton Crosstown LRT. Read more »

December 132018

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Friday, December 14, 2018 from 4:00 a.m. until 10:00 a.m. To facilitate this delivery, concrete trucks will be arriving to the site west of Ionview Road. Read more »

December 132018
December 102018

Eglinton Avenue West Lane Restriction at Cedarvale Station

What Work Is Taking Place?What Work Is Taking Place?

To accommodate the installation of tie-rods on the north side of Eglinton Avenue west of Allen Road South, crews will be restricting the curbside westbound lane on Eglinton Avenue West from Allen Road South to Park Hill Road.

Hours of Work Read more »

December 102018

Geotechnical Equipment Installation at Chaplin Cres and Russell Hill Rd

LANEWAY INTERRUPTIONS FOR GEOTECHNICAL INSTALLATION

 

What Work is Taking Place?

Beginning Tuesday December 11, crews will be working in the laneway south of Eglinton Avenue West (behind the Old Fire Hall), between Chaplin Crescent and Russell Hill Road to install geotechnical equipment.  Through access in the laneway may be unavailable while this work is taking place.

When? Read more »